[Colorado-Talk] Fwd: CDOT to close CO 60 at I-25 for 21 days for I-25 North Express Lanes Project starting Sept. 12

Gary Van Dorn garyvdrn at msn.com
Sun Sep 11 14:57:30 UTC 2022


The below announcement from CDOT sounds as though it could cause major problems for individuals in the Fort Collins and Loveland areas of our State.  I am very sure it will effect not only travel times for individuals in privately owned vehicles but also those of us who use Bustang going north.  CO 60 and I-25 is at Johnstown.

Gary

Begin forwarded message:

From: Colorado Department of Transportation News Room <dot_news at state.co.us<mailto:dot_news at state.co.us>>
Subject: CDOT to close CO 60 at I-25 for 21 days for I-25 North Express Lanes Project starting Sept. 12
Date: 8 September 2022 at 18:01:42 MDT
To: <garyvdrn at msn.com<mailto:garyvdrn at msn.com>>
Reply-To: Colorado Department of Transportation News Room <dot_news at state.co.us<mailto:dot_news at state.co.us>>

View this email in your browser<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmailchi.mp%2Fcodot.us%2Fco60closure090822%3Fe%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080093565%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=R6oEQXdmYaNXz%2FlWL0mNxi5veusUWg6wPTv%2FIcqtJhk%3D&reserved=0>
News From:
[https://mcusercontent.com/b4d4ab81cda1d77ccd692af2f/images/9c844702-b19b-a7db-2a0a-13f6d99df8ad.png]<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3Df55b790014%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080093565%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=Xhrr%2FQZVQrhoQZpWi7JxRNlr84XKbnkEmkTKWt%2BH5ao%3D&reserved=0>

Sept. 8, 2022

 Jared Fiel, NE Reg. Communications Manager
970.302.2846 | jared.fiel at state.co.us<mailto:jared.fiel at state.co.us>
CDOT to close CO 60 at I-25 for 21 days for I-25 North Express Lanes Project starting Sept. 12

WELD COUNTY – Starting Monday, Sept. 12, at 6 a.m. to Oct. 2 at 9 p.m., the Colorado Department of Transportation and the I-25 North Express Lanes Project will close eastbound and westbound Colorado Highway 60 at I-25.

There will also be various intermittent ramp closures during the 21-day closure. These closures will allow crews to complete drainage, paving and striping work necessary for the new Diverging Diamond Interchange planned for this location. After the 21-day closure, CO 60 over I-25 will be in a one-lane in each direction DDI configuration

This full closure will decrease the duration of traffic impacts and increase safety for the traveling public and crews. Please follow posted detour signage in the area. Construction activities are weather-dependent and subject to change.

Scheduled Closures and Detours:

  *   Sept. 11, 9 p.m. to Sept. 12, 10 a.m.: Northbound I-25 on-ramp from CO 60 will be closed.

  *   Sept. 12-20: Eastbound and westbound CO 60 bridges will be closed, including the southbound I-25 on-ramp and the northbound I-25 off-ramp.

     *   Link to detour map<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D1a0d230aae%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080093565%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=HrvH7LQv7CssCpIx0MQtm8FTUNUF3uZk5pqKeAlzpa8%3D&reserved=0>

  *   Sept. 21-25: Eastbound and westbound CO 60 bridges will be closed.

     *   Link to detour map<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D261cd5b25e%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080093565%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=o8ehosStMS43sO1ggdx%2BsgQxlmv68LqIc5viWRvXDps%3D&reserved=0>

  *   Sept. 26-Oct. 1: Eastbound and westbound CO 60 bridges will be closed, including all I-25 on- and off-ramps at the interchange, for two days at a time.

     *   Link to detour map<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3Dd1e59375cf%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080093565%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=lBu%2BhZbTfxoveHqZ8IZX%2B69dByNeX3yTZonr1JUFW6c%3D&reserved=0>

  *   Oct. 2: Eastbound and westbound CO 60 bridges will be closed, including all I-25 on- and off-ramps at the interchange.

     *   Link to detour map<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D44d5151368%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080093565%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=tOlT8ZLTsZX6f71iTOo9%2BWYzylImfjyvdqoGG8SA4Eg%3D&reserved=0>

Additional Closure

In addition, southbound Gateway Drive will be closed at Weld County Road 48 for paving, and the left turn lane from WCR 48 onto northbound Gateway Drive will be closed Monday, Sept. 12 at 6 a.m. to Tuesday, Sept. 20 at 5 p.m. Traffic will be diverted and detoured to Gateway Circle to the west.

While a 21-day closure will cause temporary travel impacts for residents and commuters, a full closure greatly reduces the overall duration of impacts to the traveling public. It also allows a large amount of work to be completed without continual interruptions through the remaining construction of this interchange, and it serves as a cost savings compared to inefficiencies of additional detours and partial closures.

During this maximum 21-day closure, crews will complete a variety of operations and bring the Project one step closer to another milestone. Work that will be completed during the closure includes:

  *   Drainage pipe installation

  *   Embankment work

  *   Installation of curb and gutters, islands and traffic signals

  *   Paving roadway and ramp approaches

  *   Lane striping and pavement markings

The Project team held a virtual public meeting on Monday, Aug. 22 to share information on this closure. A recording of the meeting, along with an informational video about Diverging Diamond Interchanges are available on our website<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3Ddc29c8b9d4%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=fSp8%2BU6xuRM%2F%2BqEMLdILiEXbGzVd8vlEbe4YOIupiuA%3D&reserved=0> and linked below:

I-25 North Public Meeting - CO 60 Closure<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D27aec8e502%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=jrK1LQkdpNM%2F2WrXWJs86reep%2FWeHCtSfw0pUayRH2M%3D&reserved=0>

Diverging Diamond Interchange Video<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D3ca107a187%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=PSzlp0Didn9GJTRrrABjoIREH5%2Bb1bOJQSHZ4huQRsk%3D&reserved=0>

Please visit www.codot.gov/projects/north-i-25<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D70751355c7%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=%2Bptn3%2FeBI8Gr2%2FX3lsHxA7DYfLCVKdkCFWA%2FPqVW7h0%3D&reserved=0>, for the most current travel updates. The I-25 North Express Lanes Project: Berthoud to Johnstown section will increase highway capacity by adding an Express Lane in each direction, rebuild interchanges, replace aging bridges, straighten highway curves to improve safety, make major utility and drainage improvements, and add carpool and transit facilities. During construction on the I-25 North Express Lanes Project, motorists should expect speed reductions to 65 mph, minor lane shifts, temporary concrete barriers and median bridge work. Motorists should also expect delays during the scheduled work hours. Construction on the Berthoud to Johnstown segment is expected to be complete in early 2024.

PROJECT CONTACT INFORMATION

  *   Project phone line - (720) 593-1996

  *   Project email – Northi25ExpressLanes at gmail.com<mailto:Northi25ExpressLanes at gmail.com>

  *   Project web site - www.codot.gov/projects/north-i-25<http://www.codot.gov/projects/north-i-25>

  *   Sign up for weekly project updates by logging onto the project web site and filling out the right-side form to “Subscribe to Project Updates.”

ABOUT CDOT

The Colorado Department of Transportation’s mission is to provide the best multi-modal transportation system that most effectively and safely moves people, goods and information. CDOT maintains more than 23,000 lane miles of highway, more than 3,400 bridges and 35 mountain passes. Our team of employees works tirelessly to reduce the rate and severity of crashes and improve the safety of all modes of transportation. CDOT leverages partnerships with a range of private and public organizations and operates Bustang, an interregional express bus service. Find more details at codot.gov<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D24a08f3a0d%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=ODoEMEumwC7wc67uukzDlBFdoUNpr8o1osnVUpyraGw%3D&reserved=0>.

[Twitter]<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3Db93340d82d%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=QL4h%2B02gfFvZH9roksxvWKQNcUUptMCSdOkfERumh18%3D&reserved=0>
[Facebook]<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3Ddd6b5df0b5%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=xf5yp%2Bx4%2By87qW4B%2FkTlISCys1aSTQRaYjyn8gWBoxc%3D&reserved=0>
[Instagram]<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3De89fb92bd2%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=KKyzu4WXKuiekrtlPmGPqOGKh%2B2Y%2BNSEO%2FfZzP5zog8%3D&reserved=0>
[YouTube]<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D7bc601eb6c%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=%2FNtCdHhuBNPqyHoisU17Ou4UM37Obzyiv5WByFKepe0%3D&reserved=0>
[Website]<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Ftrack%2Fclick%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3Dd64c4e9e20%26e%3Daff74b646e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=l8NWPwrKS727Jol%2FgN1xNIWN5fRTNbaE39k%2FP4yZ09k%3D&reserved=0>
Copyright © 2022 Colorado Department of Transportation, All rights reserved.
You are receiving this email because you subscribed to receive news and press releases from CDOT.

Our mailing address is:
Colorado Department of Transportation
2829 W Howard Pl
Denver, CO 80204-2305

Add us to your address book<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Fvcard%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D6f4d3d430b&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=McKc9b%2B%2BtjwihJQmAvNgw8upEuJNErHaycGl5sUtn%2FE%3D&reserved=0>


Want to change how you receive these emails?
You can update your preferences<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Fprofile%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D6f4d3d430b%26e%3Daff74b646e%26c%3D912c46a33e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=c2NPDAfw0aGjwLUGHihcOFpYOwNQiSZyMYSwbOOnBj0%3D&reserved=0> or unsubscribe from this list<https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fstate.us16.list-manage.com%2Funsubscribe%3Fu%3Db4d4ab81cda1d77ccd692af2f%26id%3D6f4d3d430b%26e%3Daff74b646e%26c%3D912c46a33e&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=o6dkShnyNa1ZmM9W4ICZ95GPAy2i3ynM7p7sduJrfDg%3D&reserved=0>.

[Email Marketing Powered by Mailchimp]<https://nam12.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.mailchimp.com%2Femail-referral%2F%3Futm_source%3Dfreemium_newsletter%26utm_medium%3Demail%26utm_campaign%3Dreferral_marketing%26aid%3Db4d4ab81cda1d77ccd692af2f%26afl%3D1&data=05%7C01%7C%7C17baa16eb5104b072ffd08da91f67b50%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C637982785080249780%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=gOnHE6ocxAolUs9NNvWhl08tyFV0LUAZMLtF5T%2BWJ3o%3D&reserved=0>


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://nfbnet.org/pipermail/colorado-talk_nfbnet.org/attachments/20220911/ebf6093b/attachment.html>


More information about the Colorado-Talk mailing list