[Colorado-Talk] Fwd: Stratavault Update, Current Activities

Gary Van Dorn garyvdrn at msn.com
Wed Sep 20 22:34:41 UTC 2023



Begin forwarded message:

From: 16th Street Mall Updates <16thstreetmall at denvergov.org>
Subject: Stratavault Update, Current Activities
Date: September 19, 2023 at 15:59:36 MDT
To: <garyvdrn at msn.com>
Reply-To: 16th Street Mall Updates <16thstreetmall at denvergov.org>

View this email in your browser<https://mailchi.mp/73b72f17eab2/16th-street-mall-pre-construction-activities-update-10450045?e=0e4069ae0b>
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/d0b3d028-caf1-b6bd-cacf-0d1ccfd256a4.png]
One Step Closer to Trees in Block 2!

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/06e7e4d9-1f52-1cb0-325b-bf630cca8ebd.png]
We're excited to share progress between Larimer and Lawrence Streets! Our team has started building the stratavault system, a vital step for planting new trees. This innovative technology will allow for the healthy development of the new tree canopy next to the transit wall infrastructure. Building the stratavault system for the trees includes grading, stratavault install, planting material installation and irrigation. In the image on the left, you can see the electrical and irrigation conduit and the wooden boxes which will be the pits where the trees are planted. The rendering of the right illustrates how the stratavualt system will operate once the project is complete. To stay up-to-date on progress, you can check the current project activities page on the website<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=e74a8b838d&e=0e4069ae0b>.
Current Project Activities

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/e4aac9bd-7f37-127b-e531-3bee7c1fc3f8.jpg]
Market to Larimer (Block 1)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=fe659752b5&e=0e4069ae0b>
  *   Market Intersection:
     *   Right-lane closure and east crosswalk for concrete work began Sept. 11, lasting through the end of October

Larimer to Lawrence (Block 2)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=07e9588383&e=0e4069ae0b>
  *   Larimer intersection:
     *   West sidewalk closure began Sept. 5, lasting through the end of October

Lawrence to Arapahoe (Block 3)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=232f883a44&e=0e4069ae0b>
  *   Lawrence intersection:
     *   East crosswalk closure began July 19, lasting through late October

Arapahoe to Curtis (Block 4)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=01d52c34dd&e=0e4069ae0b>
     *   Full closure of south sidewalk began April 20, lasting through fall 2023, when sidewalk area is moved to transitway
  *   Arapahoe intersection:
     *   Single left-lane closure and east crosswalk shift on Arapahoe began July 19, lasting through mid-November
     *   West crosswalk closure began July 19, lasting through mid-November
     *   This intersection will have various crosswalk closures for the duration of this work. At least three of the four crosswalks are open at all times

Curtis to Champa (Block 5)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=bbbb82659b&e=0e4069ae0b>
  *   Curtis intersection:
     *   Double, left-lane closure for  sleeper slab and conduit installation began Aug. 4, lasting through late September
     *   This intersection will have various crosswalk closures for the duration of this work. At least three of the four crosswalks are open at all times

Champa to Stout (Block 6)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=597cf3ab0e&e=0e4069ae0b>
     *   Full block, curb-to-curb fencing being installed this week
  *   Champa Intersection:
     *   Full intersection closure began Sept. 6, lasting for a minimum of nine weeks
        *   Bike lane temporarily detoured to the Arapahoe intersection between 14th and 18th streets
        *   This intersection will have various crosswalk closures for the duration of this work. At least three of the four crosswalks are open at all times

Stout to California (Block 7)

  *   Utility work underway
     *   Half block, curb-to-curb fence on the west side of the block, along with the narrowed north sidewalk and alley closure began Sept. 11, lasting for several weeks

California to Welton (Block 8)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=9da6346cea&e=0e4069ae0b>

Welton to Glenarm (Block 9)

  *   Utility work underway:
     *   Work for water and sewer lines began May 16, lasting through mid-October
        *   Fencing encloses work from curb to curb for the entire block
        *   Fencing will adjust outward based on current activity in the block
  *   Welton intersection:
     *   Double-lane closures for water and storm sewer work began Sept. 7, lasting through at least mid-October. One northbound lane is open

Glenarm to Tremont (Block 10)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=c273b5d091&e=0e4069ae0b>

  *    Glenarm intersection:
     *   Temporary fencing in full intersection began August 17, lasting for approximately 10 weeks
        *   The west crosswalk will be closed, but the other three crosswalks in the intersection will remain open
        *   Bike lanes temporarily detoured to Welton and Tremont intersections at 15th and 17th streets

Court to Cleveland (Block 12)

  *   Utility work underway
     *   Half-block fence on the west end of the block began Sept. 7, lasting through early October
        *   South sidewalk and transit lane closed to pedestrians between Court Place and the Sheraton parking garage entrance

Expected Work Hours

Workdays and hours are anticipated to be Monday through Friday, 7 a.m. to 5 p.m. Weekend work will occur between 8 a.m. and 5 p.m. Heavy equipment may operate between hours of 8 a.m. to 5 p.m., any day of the week. Material deliveries and staging may occur overnight. All project activities and schedules are weather-dependent and subject to change.

Due to schedule and sequencing, not all active blocks will have activities occurring at all times. To see the latest updates on work, you can check the current project activities page on the website<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=aa4dbf8290&e=0e4069ae0b>.
RTD Free MallRide

The RTD Free MallRide continues to run during the 16th Street Mall Project, rerouted to 15th and 17th streets until the project is complete. The detour is currently from Wazee Street to Civic Center Station. For more information on RTD's Free MallRide detours, visit rtd-denver.com/app/alerts/routes/MALL<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=89338d95d3&e=0e4069ae0b>.

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/3c60f5ac-cb97-8b04-4b92-aa5a3301b19d.jpg]
Business Support

The City and County of Denver and the Downtown Denver Partnership have developed a Small Business Support Program<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=86ab8a49a8&e=0e4069ae0b> to assist businesses potentially impacted by 16th Street Mall construction throughout the multi-year construction period. Check if your business is now eligible on the Business Support page<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=250c313c84&e=0e4069ae0b> of the 16th Street Mall Project website. Questions? Email edprograms at downtowndenver.com<mailto:edprograms at downtowndenver.com>.
Connect with the Project Team

Trailer Talks
To meet 16th Street Mall visitors where they are, project team members will staff a mobile kiosk on the Mall to provide project information and answer questions from the public. Find us at the MyDenver Street Activation outside of the Paramount Theater on Glenarm Place on Wednesday, Sept. 27, from 11:00 a.m. - 1:00 p.m. We hope to see you there!

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/f89662d4-68a3-0e0a-15bb-41492601f16c.png]Mobile App
Need 16th Street Mall information on the go? Download our mobile app to:

  *   Access the overview map of all project activities
  *   Learn about the project and each construction phase
  *   Find businesses along the Mall
  *   Sign up for block-by-block notifications on construction impacts, phase changes and more to best plan your route
  *   Connect with the project team with concerns or questions from your mobile device

To download the app, go to the Apple Store or Google Play store and search “16th Street Mall Project."

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/454f9048-2b45-d5ef-ed24-8ccc45019d76.png]
 Clean & Safe Mobile App

Directly report non-emergency public safety and maintenance concerns in Downtown Denver. The Clean & Safe Program covers the Business Improvement District for the 120 blocks of Downtown Denver, including LoDo, Upper Downtown and the Convention Center corridor.

To download the app, go to the Apple Store or Google Play store and search “Clean & Safe - Downtown Denver."

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/30d5bd02-487a-10d4-b339-a013f03283be.jpg]















This email was sent to garyvdrn at msn.com<mailto:garyvdrn at msn.com>
why did I get this?<https://cig-pr.us1.list-manage.com/about?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&e=0e4069ae0b&c=97cbd594da>    unsubscribe from this list<https://cig-pr.us1.list-manage.com/unsubscribe?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&e=0e4069ae0b&c=97cbd594da>    update subscription preferences<https://cig-pr.us1.list-manage.com/profile?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&e=0e4069ae0b&c=97cbd594da>
CIG PR · 1660 Lincoln St Ste 1800 · Denver, CO 80264-9906 · USA



-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://nfbnet.org/pipermail/colorado-talk_nfbnet.org/attachments/20230920/a9767f66/attachment.html>


More information about the Colorado-Talk mailing list