Subject: 16th Street Mall | Block 6 Phase 2 Transition, Current Activities

View this email in your browser<https://mailchi.mp/d20043f5fef6/16th-street-mall-pre-construction-activities-update-11029744?e=0e4069ae0b>
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/77077e47-7017-b193-05fb-f2bdc0b429a6.png]

The 16th Street Mall Project team is deeply saddened by the violent acts that occurred near 16th Street this past weekend. Our hearts go out to the victims, their loved ones and the entire downtown community.

Safety remains a top priority for the project team as we continue to work closely with the City of Denver, the Downtown Denver Partnership and the Denver Police Department to promote security on and around the project site.

In the wake of this tragedy, we remain committed to creating a welcoming and vibrant 16th Street as we move toward project completion this year.

Phase 2 Transition Between Champa and Stout Streets

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/ff3840c5-cca2-ced2-d816-6a8537646392.jpg]
Phase 2 of construction on Block 6 between Champa and Stout streets is scheduled to begin as soon as today (Wednesday, Jan. 15) and last three to four months. This phase includes installing the new granite pavers on the sidewalks and will require a change in the fencing layout. The image above is a general example of Phase 2 work and fencing.

The first thing you will see is crews beginning to adjust the fence gradually to achieve the layout described below. Signage will direct pedestrians to business access points.

You can expect:

  *   East half of the block:
     *   North and south sidewalks enclosed with pedestrians routed to the center transitway
     *   Five-foot walkways will provide access to businesses
  *   West half of the block:
     *   South sidewalk enclosed and north sidewalk open
     *   Five-foot walkways will provide access to businesses
  *   This fencing configuration will move as work progresses, and five-foot walkways leading to businesses may be closed intermittently outside of business hours for work occurring in those areas. Business access will always be maintained while businesses are open.
  *   Wayfinding signage will be installed on the fencing to direct pedestrians to businesses.

Sawcutting & Demolition

This activity may be noisy at times as sawcutting and demolition breaks up the concrete slab, but the project team will stay within the City’s noise ordinance as we recognize we are working in close proximity to businesses and residents.  All construction activities are schedule and weather-dependent and subject to change.

All construction activities are schedule and weather-dependent and subject to change.

Current Project Activities

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/29e56f5a-cbcd-6b6a-d25e-9ee4bab39ee5.jpg]
Project Activity Overview:

  *   All construction activities are schedule and weather-dependent and subject to change
  *   Work may require intermittent lane closures at intersections between Wazee and Broadway throughout construction. Pedestrian and business access will be maintained
  *   Intersections will have various crosswalk closures for the duration of the project. At least three of the four crosswalks will be open at all times. Follow signage and plastic water barriers, where present, to a safe crossing location

Market to Curtis (Blocks 1-4)

  *   Reconstruction improvements complete!

Curtis to Champa (Block 5)

  *   Phase 3 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=ffc94dbb09&e=0e4069ae0b>
     *   Fences or construction cones will occupy isolated areas within the block where work is taking place for short periods of time
  *   Curtis intersection:
     *   Single, left-lane closure on Curtis Street to accommodate the turning radius of the RTD Free MallRide shuttles. This began Sept. 14, 2024, and will remain while the MallRide detour is in this configuration

Champa to Stout (Block 6)

  *   Phase 2 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=d92559ebb0&e=0e4069ae0b>
     *   East half of the block
        *   North and south sidewalks enclosed with pedestrians routed to the center transitway
        *   Five-foot walkways will provide access to businesses
     *   West half of the block
        *   South sidewalk enclosed and north sidewalk open
        *   Five-foot walkways will provide access to businesses
  *   Champa intersection:
     *   Single, left-lane closure on Champa Street began Sept. 16, 2024, lasting through March

Stout to California (Block 7)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=7115345406&e=0e4069ae0b>
     *   South sidewalk closure on east half of block began Nov. 25, 2024, lasting through summer
  *   Stout intersection:
     *   Single, right-lane closure began Aug. 24, 2024, lasting through summer

California to Welton (Block 8)

  *   Phase 2 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=8c95b82925&e=0e4069ae0b>
  *   California intersection:
     *   Full intersection closure began Jan. 2, lasting through late-January. See detour map here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=a20bfde78e&e=0e4069ae0b>

Welton to Glenarm (Block 9)

  *   Phase 2 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=ec4e48f178&e=0e4069ae0b>
  *   Welton intersection:
     *   Welton Street is operating as a one-way, northbound street between 15th and 17th Streets
     *   Double-lane closure on Welton Street began Sept. 25, 2024, lasting through spring. Various traffic configuration shifts will occur with one northbound lane and bike lane remaining open at all times

Glenarm to Tremont (Block 10)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=663c08838f&e=0e4069ae0b>
  *   Glenarm intersection:
     *   Northbound bikes on Glenarm Place are detoured to Welton Street. Southbound bikes are detoured to Tremont Place

Tremont to Court (Block 11)

  *   Phase 1-2 Combo<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=3f96eef657&e=0e4069ae0b> (north side only) improvements underway
     *   North side businesses can be accessed through walkways from Tremont Place and Court Place
  *   Tremont intersection:
     *   Single, left-lane closure began Dec. 9, 2024. Lane closures with several traffic configuration shifts occurring will continue on Tremont Place through summer. One southbound lane will remain open at all times
     *   The bike lane on Tremont Place is open

Court to Cleveland (Block 12)

  *   Phase 1-2 Combo<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=d524a886d5&e=0e4069ae0b> (south side only) improvements underway
     *   South side businesses can be accessed from the north sidewalk through a walkway in the center of the block.
  *   Court intersection:
     *   Double, right-lane closure began July 25, 2024, lasting through late-January
        *   This will be followed be a double, left-lane closure lasting through early-April

Cleveland to Broadway (Block 13)

  *   Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=fbcde40a47&e=0e4069ae0b>
  *   Cleveland intersection:
     *   Full intersection closure began Sept. 30, 2024, lasting through April. See detour map here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=d232daf754&e=0e4069ae0b>
     *   See bike lane detour <https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=b22d36ccf4&e=0e4069ae0b> here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=6bf05f0204&e=0e4069ae0b>.<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=c1bcde700e&e=0e4069ae0b> Bicyclists who remain on Cleveland Place and East 16th Avenue must dismount and use the crosswalks and sidewalk

Expected Work Hours

Workdays and hours are anticipated to be Monday through Friday, 7 a.m. to 9 p.m. Weekend work will occur between 8 a.m. and 5 p.m.

A noise variance was approved in January 2024 which allows work to take place throughout the night under specific circumstances<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=48114b567d&e=0e4069ae0b>. Affected parties will be notified 7 days in advance if night work will be taking place.

Heavy equipment may operate between hours of 8 a.m. to 5 p.m., any day of the week. Material deliveries and staging may occur overnight. All project activities and schedules are weather-dependent and subject to change.

Due to schedule and sequencing, not all active blocks will have activities occurring at all times. To see the latest updates on work, you can check the Current Project Activities<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=28508e1d54&e=0e4069ae0b> page<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=0f90a58850&e=0e4069ae0b> on the website.
RTD Free MallRide

The RTD Free MallRide continues to run during the 16th Street Mall Project. Shuttles operate on a portion of 16th Street between Union Station and Curtis Street. The Free MallRide continues to be rerouted to 15th and 17th streets between Curtis Street and Civic Center Station. For more information on RTD's Free MallRide detours, visit RTD's Free MallRide detours page<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=09561524bc&e=0e4069ae0b>.

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/18c800c0-ff14-c1b2-baf8-137b7b0d7c1f.jpg]

Business Support

The City and County of Denver and the Downtown Denver Partnership have developed a Small Business Support Program<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=db0010b849&e=0e4069ae0b> to assist businesses potentially impacted by 16th Street Mall construction throughout the multi-year construction period. Check if your business is now eligible on the Business Support page<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=8137a79c10&e=0e4069ae0b> of the 16th Street Mall Project website. Questions? Email ddpgrants at downtowndenver.com<mailto:edprograms at downtowndenver.com>.
Connect with the Project Team

Virtual Office Hours

Each month, project team members will host virtual office hours to provide project information and answer questions from the public. The next virtual office hours will be held on Jan. 23, 2024 from noon – 12:30 p.m. RSVP and receive a meeting link here.<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=fd99dc4adb&e=0e4069ae0b> If that time won’t work with your schedule, we are also happy to set up a different time to meet in-person or virtually.

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/f89662d4-68a3-0e0a-15bb-41492601f16c.png]Mobile App
Need 16th Street Mall information on the go? Download our mobile app to:

  *   Access the overview map of project activities
  *   Learn about the project and each construction phase
  *   Find businesses along the Mall
  *   Sign up for block-by-block notifications on construction impacts, phase changes and more to best plan your route
  *   Connect with the project team with concerns or questions from your mobile device

To download the app, go to the Apple Store or Google Play store and search “16th Street Mall Project."

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/454f9048-2b45-d5ef-ed24-8ccc45019d76.png]
 Clean & Safe Mobile App

Directly report non-emergency public safety and maintenance concerns in Downtown Denver. The Clean & Safe Program covers the Business Improvement District for the 120 blocks of Downtown Denver, including LoDo, Upper Downtown and the Convention Center corridor.

To download the app, go to the Apple Store or Google Play store and search “Clean & Safe - Downtown Denver."

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/_compresseds/8ddaf6a7-9081-a293-8efd-085d52a682bf.jpg]















This email was sent to garyvdrn at msn.com<mailto:garyvdrn at msn.com>
why did I get this?<https://cig-pr.us1.list-manage.com/about?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&e=0e4069ae0b&c=f1aa132660>    unsubscribe from this list<https://cig-pr.us1.list-manage.com/unsubscribe?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&t=b&e=0e4069ae0b&c=f1aa132660>    update subscription preferences<https://cig-pr.us1.list-manage.com/profile?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&e=0e4069ae0b&c=f1aa132660>
CIG PR · 1660 Lincoln St Ste 1800 · Denver, CO 80264-9906 · USA

 ͏  ͏  ͏  ͏ ͏  ͏  ͏  ͏ ͏  ͏  ͏  ͏ ͏  ͏  ͏  ͏ ͏  ͏  ͏  ͏ ͏  ͏  ͏  ͏

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://nfbnet.org/pipermail/colorado-talk_nfbnet.org/attachments/20250115/2a1b0ec4/attachment.htm>


More information about the Colorado-Talk mailing list