[nfbwatlk] FW: [PEDMASTERPLAN] Rainier Transit Priority Corridor Improvements (TPCI) Project Update

Jacob Struiksma lawnmower84 at hotmail.com
Thu Sep 30 21:57:38 UTC 2010


 

Rainier Transit Priority Corridor Improvements (TPCI)

 

Project Update - September 29, 2010

 

S Jackson Street & Maynard Avenue S (south side)

Work is substantially complete and the bus stop has been reopened.

 

S Jackson Street & 12th Avenue S (south side)

Work is expected to be substantially complete within 1-2 weeks.  The bus
stop is scheduled to re-open on October 7th.

 

Rainier Ave S & Martin Luther King Jr. Way (MLK) S

Work is progressing in this area.  The overall project construction is still
expected to be substantially complete by the end of December 2010.

 

Rainier Avenue S & S Genesee Street

Construction work is progressing in the area of Rainier Avenue S & S Genesee
Street (west and east sides). There are temporary bus stop closures, partial
traffic lane closures and parking restrictions on Rainier Avenue S, S
Genesee Street and 36th Avenue S, near the work area.  Access will be
maintained to businesses.

 

Eastbound S Genesee Street is closed at Rainier Avenue S and will remain
closed through October.  A traffic detour will direct vehicles South to S
Oregon Street and north to S Dakota Street The work is expected to take
approximately 5-6 additional weeks to complete.

 

Rainier Avenue S & 39th Avenue S

Work has started and is progressing in the area of Rainier Avenue S & 39th
Avenue S.  There are temporary bus stop relocations, partial traffic lane
closures and/or parking restrictions on Rainier Avenue S and a full street
closure on 39th Avenue S near the work area.  Access will be maintained to
businesses.  The work is expected to take approximately 6-7 additional weeks
to complete.  

 

Rainier Avenue S & S Orcas Street

Construction work has started work in the area of Rainier Avenue S & S Orcas
Street.  There are temporary bus stop relocations, partial traffic lane
closures and/or parking restrictions, on Rainier Avenue S and S Orcas
Street, near the work area.  Access will be maintained to businesses.  The
work is expected to take approximately 5 to 6 additional weeks to complete.

 

S Jackson Street & 8th Avenue S (south side) and S Jackson Street & Maynard
Avenue S (north side)

Beginning the week of October 4th construction work will begin in the area
of S Jackson St at 8th Ave S, and on October 7th, at the northwest side of
Maynard Ave S.  Work in these areas is expected to take 5 to 6 weeks to
complete.

 

Local businesses are open during construction and the community is
encouraged to stop and shop.  

 

For more information, or if you would like to receive regular project
updates, please visit SDOT's website at:

 <http://www.seattle.gov/transportation/tpci_rainier.htm>
http://www.seattle.gov/transportation/tpci_rainier.htm

 

 

Privacy and Mailing List  <http://www.seattle.gov/pan/> Policy
List-Unsubscribe
<mailto:pedmasterplan-unsubscribe-request at talk2.seattle.gov>  |
List-Subscribe <mailto:pedmasterplan-subscribe-request at talk2.seattle.gov>  |
List-Owner  <mailto:pedmasterplan-request at talk2.seattle.gov> 




More information about the NFBWATlk mailing list