[Colorado-Talk] Fwd: Arapahoe Intersection Closure, Block 5 Renovations, Current Project Activities

Gary Van Dorn garyvdrn at msn.com
Wed Mar 15 18:37:04 UTC 2023



Sent from my iPad

Begin forwarded message:

From: 16th Street Mall Updates <16thstreetmall at denvergov.org>
Date: March 15, 2023 at 12:14:38 MDT
To: garyvdrn at msn.com
Subject: Arapahoe Intersection Closure, Block 5 Renovations, Current Project Activities
Reply-To: 16th Street Mall Updates <16thstreetmall at denvergov.org>


View this email in your browser<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmailchi.mp%2F90c335824f27%2F16th-street-mall-pre-construction-activities-update-10418737%3Fe%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783118927%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=EmvGuK7LRIzzkrKdt1ZXLdcv%2B4IbyPS3fnUKBxULmQQ%3D&reserved=0>
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/d0b3d028-caf1-b6bd-cacf-0d1ccfd256a4.png]
Arapahoe and 16th Streets Intersection Closure

The intersection at Arapahoe and 16th streets will temporarily close as soon as March 20 and will remain closed for approximately one month. Arapahoe will become a two-way street between 15th and 16th streets and between 16th and 17th streets during the intersection closure, with a U-turn required at the 16th Street Mall intersection. A temporary signal will be installed at 17th Street. On-street parking will be limited along Arapahoe Street. Business and residential access, including access to parking structures, loading docks and surface lots will be maintained. Please see the detour map<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3D3133d6334f%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783118927%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=C3sYKcaWvDiihjte4zXYoLZfGcyb1qz1VYuoJLoPZmI%3D&reserved=0>.

Renovations to start between Curtis and Champa streets
As soon as March 27, you can expect to see full construction fencing placed between Curtis and Champa streets, marking the start of the 18 months of reconstruction work.

Work days and hours are anticipated to be Monday through Friday, 7 a.m. to 5 p.m. Weekend work will occur between 8 a.m. and 5 p.m. Material deliveries and staging may occur overnight. Work and schedules are weather-dependent and subject to change.

Here’s what you can expect during the first phase of activity, which will last approximately 13-14 months:  

  *   Work begins in the center transitway area.
  *   Pedestrian walkways and access to storefronts will be maintained on both sides of the Mall, but walkways will be narrower.
  *   Curb-to-curb fencing will be installed initially and will move out as construction activities change.
  *   Fencing will surround the work site and include signs to direct people traveling on the Mall.
  *   Gates and flaggers will be on-site at intersections to direct drivers and pedestrians as needed.
  *   All businesses will remain accessible.

Current Project Activities

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/3a9f12fe-0ed7-54ed-ab7d-9b0a3e62fd2d.png]

Market to Larimer (Block 1)

  *   Phase 1 of improvements underway<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3D389867e2d4%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783118927%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=KYg6ogPO%2F4Ezh2VoFV0L51OJI6rAZqDPVn0w0J1AGRc%3D&reserved=0>
  *   Market intersection:
     *   Intermittent single-lane closures on Market Street for deliveries through March 22
  *   Utility work to start as soon as March 22
     *   Double-lane closure for water and storm sewer work lasting for a few months

Larimer to Lawrence (Block 2)

  *   Phase 1 of improvements underway<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3De027913f2c%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783118927%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=%2Fb%2BBCjSJbhpi5OnqEHW%2FfyLhRPiw927RcuICXhd1Gk0%3D&reserved=0>

Lawrence to Arapahoe (Block 3)

  *   Phase 1 of improvements underway<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3D3b847199c9%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=i83cQ2Dhq3YAHKadpUX6r%2BdUNGN%2FXiRi2zbRF9t9HDg%3D&reserved=0>
  *   Lawrence intersection:
     *   Single-lane closure for water and storm sewer work lasting through late March

Arapahoe to Curtis (Block 4)

  *   Phase 1 of improvements underway<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3Da287f04b27%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=B90dComTb3nzs5doXcmFGLz1wCDt9K1BRm%2FAHAs6EiU%3D&reserved=0>
     *   Full closure at the intersection of Arapahoe and 16th streets as soon as March 20, lasting for approximately one month. See detour map<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3Dcb96e3de7c%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=bE1wPlAXl244hcilv1IsbU1qYv6xKS0uXud0gTRzzdA%3D&reserved=0>.
  *   Arapahoe intersection:
     *   Double-lane closure for water and storm sewer work lasting through mid-March

Curtis to Champa (Block 5)

  *   Curtis intersection:
     *   Lane closure as soon as March 27 for several weeks for utility work, parking lane will also be closed. One travel lane will be maintained.
  *   Reconstruction is to begin as soon as late-March
     *   Fencing will enclose work from curb to curb for the entire block
     *   Fencing will adjust outward as construction activities change.

California to Welton (Block 8)

  *   Utility work underway
     *   Work for water and sewer lines began March 9 lasting for several months
        *   Fencing will enclose work from curb to curb for the entire block
        *   Fencing may adjust outward based on current activity in the block

Welton to Glenarm (Block 9)

  *   Welton intersection:
     *   Double-lane closure on Welton Street for gas line work through mid-April
        *   Northbound traffic will be maintained at all times. No southbound traffic between 17th and 16th streets; limited southbound traffic between 16th and 15th streets.
  *   Utility work to begin as soon as late March between Welton and Glenarm lasting for several months

Work Hours

  *   Monday through Friday, 7 a.m. to 5 p.m.;
  *   Weekend work between 8 a.m. and 5 p.m. can also be anticipated; and
  *   Material deliveries and staging may occur overnight.

Construction work and schedules are weather-dependent and subject to change. For updated information, visit our website at denvergov.org/16thStreetMall<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3D74d53b7fc6%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=dL%2BR%2BVnr3K9ua3mqLmzzluCeE9ZXwpHrNdZ%2BDYSyq0Q%3D&reserved=0>.

RTD Bus Routes
The RTD Free MallRide shuttle continues to run during the 16th Street Mall Project, rerouted to 15th and 17th streets until the project is complete. The detour is currently from Wazee Street to Civic Center Station. For more information on RTD's Free MallRide detours, visit rtd-denver.com/app/alerts/routes/MALL<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3D9f82cdfdc4%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=KzGdMtHZtFyckv63%2B1juaGZZZZ0uku%2FdT%2B50lXUbXTo%3D&reserved=0>.

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/3c60f5ac-cb97-8b04-4b92-aa5a3301b19d.jpg]
Business Support

The City and County of Denver and the Downtown Denver Partnership have developed a Small Business Support Program<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3D858ced0bac%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=eAjgT19bOgVw6HQLWIllCPAGc35h0L5x3o5gwyog82M%3D&reserved=0> to assist businesses potentially impacted by 16th Street Mall construction throughout the multi-year construction period. Check if your business is now eligible on the Business Support page<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Ftrack%2Fclick%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3D51d00cca15%26e%3D0e4069ae0b&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=%2FnQPloWoW6DEPyQdj6JCJkw5cPYZpifag5BLKL5hsfQ%3D&reserved=0> of the 16th Street Mall Project website. Questions? Email edprograms at downtowndenver.com<mailto:edprograms at downtowndenver.com>.
Connect with the Project Team

Trailer Talks
To meet 16th Street Mall visitors where they are, project team members will staff a mobile kiosk on the Mall to provide project information and answer questions from the public. Find us at the Outer Space area at 16th and Welton streets on Thursday, March 23, from noon to 1 p.m. We hope to see you there!

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/454f9048-2b45-d5ef-ed24-8ccc45019d76.png]
 Clean & Safe Mobile App

Directly report non-emergency public safety and maintenance concerns occurring in the Downtown Denver area. The Clean and Safe Program covers the Business Improvement District for the 120 blocks of Downtown Denver, including LoDo, Upper Downtown, and the Convention Center corridor.

To download the app, go to the Apple Store or Google Play store and search “Clean & Safe - Downtown Denver."

[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/f89662d4-68a3-0e0a-15bb-41492601f16c.png]Mobile App
Need 16th Street Mall information on the go? Download our mobile app to:

  *   Access the overview map of all project activities.
  *   Learn about the project and each construction phase.
  *   Find businesses along the Mall.
  *   Sign up for block-by-block notifications on construction impacts, phase changes and more to best plan your route.
  *   Connect with the project team with concerns or questions from your mobile device.

To download the app, go to the Apple Store or Google Play store and search “16th Street Mall Project."
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/30d5bd02-487a-10d4-b339-a013f03283be.jpg]















This email was sent to garyvdrn at msn.com<mailto:garyvdrn at msn.com>
why did I get this?<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Fabout%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3Db99fd40a0e%26e%3D0e4069ae0b%26c%3Dcb00983391&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=9UnvtTUj6jccpOk1zN%2Bn8%2BH7tC13VgXe%2BQZVkqJTiuw%3D&reserved=0>    unsubscribe from this list<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Funsubscribe%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3Db99fd40a0e%26e%3D0e4069ae0b%26c%3Dcb00983391&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=aB9KLq3enfIS3eawuG91FuFnbBbHzMO6VqvN9IzVOz0%3D&reserved=0>    update subscription preferences<https://na01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcig-pr.us1.list-manage.com%2Fprofile%3Fu%3Dfc34ba15e6547b8d998f63f6a%26id%3Db99fd40a0e%26e%3D0e4069ae0b%26c%3Dcb00983391&data=05%7C01%7C%7C957ad95afa4f4fab783008db258120f7%7C84df9e7fe9f640afb435aaaaaaaaaaaa%7C1%7C0%7C638145008783275233%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=Hy5u7QW4VQwLS5rgI%2FQ8jHgyG%2BuqCPU8NsOUsMzfxT4%3D&reserved=0>
CIG PR · 1660 Lincoln St Ste 1800 · Denver, CO 80264-9906 · USA


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://nfbnet.org/pipermail/colorado-talk_nfbnet.org/attachments/20230315/b1c1c2ac/attachment.html>


More information about the Colorado-Talk mailing list