I am forwarding the latest update on the Sixteenth Mall Project.
Gary
Begin forwarded message:
From: 16th Street Mall Updates <16thstreetmall at denvergov.org>
Subject: Spring has Sprung, Renovations to Begin Between Cleveland and Broadway, Current Project Activities
Date: March 19, 2024 at 16:29:29 MDT
To: <garyvdrn at msn.com>
Reply-To: 16th Street Mall Updates <16thstreetmall at denvergov.org>
View this email in your browser<https://mailchi.mp/6157137f7fda/16th-street-mall-pre-construction-activities-update-10927167?e=0e4069ae0b>
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/77077e47-7017-b193-05fb-f2bdc0b429a6.png]
Spring has Sprung on 16th Street!
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/_compresseds/a292d7a5-c8dd-13f5-d918-b3f999341a3b.jpg]
Today marks the first day of spring, and the project team is looking forward to the progress that's soon to come to 16th Street during this season of growth! Below are a few of the project milestones you can expect to see this spring:
* All thirteen blocks between Market Street and Broadway will be under active construction.
* Trees will be planted between Lawrence and Curtis streets. (Blocks 3-4)
* Granite pavers will be completed between Market and Larimer streets. (Block 1)
* Phase 2 of construction will begin between Lawrence and Arapahoe streets. (Block 3)
* Phase 2 of construction will begin on the north side of the block between Arapahoe and Curtis streets. (Block 4)
* Substantial completion will be reached between Larimer and Lawrence streets! (Block 2)
Stay tuned on the project website for frequent updates on current activities and milestone progress<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=d15e9b9968&e=0e4069ae0b>. Each block's schedule and milestones can be viewed in the block-by-block drop downs on the Current Project Activities page<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=8c83fb93b5&e=0e4069ae0b>.
Renovations to Begin Between Cleveland Place
and Broadway
As soon as Monday, March 25, crews and equipment will arrive between Cleveland Place and Broadway (Block 13) to begin Phase 1 of reconstruction work in the block. The first thing you will see is the installation of construction fencing on the entire block between 16th Street, Cleveland Place and Broadway, leaving the south sidewalk open for pedestrians. See the image below for more information.
Here's what you can expect:
* Fencing will surround the work site and include signs to direct pedestrians traveling on the Mall.
* Gates and flaggers will be on-site at intersections to direct drivers and pedestrians as needed.
* See bike detour here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=f55674513a&e=0e4069ae0b>. Bicyclists who remain on Cleveland Place and East 16th Avenue must dismount and use the crosswalks and sidewalk.
* Business access will be maintained at all times.
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/b18ec006-0ca5-54dc-9d82-e4450011f0ef.png]
The start of reconstruction activity may be noisy at times as sawcutting and demolition breaks up the concrete slab, but the project team will stay within the City’s noise ordinance as we recognize we are working close to businesses and residents.
Current Project Activities
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/f81fc1db-6f90-0192-1e6b-bd864a9b2be6.jpg]
General Project Activity Notes:
* All construction activities are schedule and weather-dependent and subject to change
* Work may require intermittent lane closures at intersections between Wazee and Broadway throughout construction. Pedestrian and business access will be maintained
* Intersections will have various crosswalk closures for the duration of the project. At least three of the four crosswalks will be open at all times. Follow signage to a safe crossing location
Market to Larimer (Block 1)
* Phase 1-2 Combo<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=24440f53d2&e=0e4069ae0b> (north side only) improvements underway
* Full closure of north sidewalk began Oct. 23, lasting through the spring
* South sidewalk remains open
* Market intersection:
* Single, right-lane closure on Market began Sept. 11, lasting through the spring
Larimer to Lawrence (Block 2)
* Phase 2 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=6c1c02d2f8&e=0e4069ae0b>
* North and south sidewalks are closed with pedestrians routed to walkway in center transitway.
* Five-foot walkways will provide access from center walkway to businesses on either side of 16th Street
* Larimer intersection:
* Double, left-lane closure on Larimer began on Feb. 15, lasting through mid-April
* Three of the four crosswalks at each intersection will remain open. Follow signage and plastic water barriers to a safe crossing location
Lawrence to Arapahoe (Block 3)
* Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=43124a8878&e=0e4069ae0b>
* Lawrence intersection:
* Single, left-lane closure on Lawrence began on Feb. 15, lasting through early-April
* Three of the four crosswalks at each intersection will remain open. Follow signage and plastic water barriers to a safe crossing location
Arapahoe to Curtis (Block 4)
* Phase 1-2 Combo<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=14bf31f6c6&e=0e4069ae0b> (south side only) improvements underway
* Full closure of south sidewalk began April 20, 2023, lasting through the spring
* Arapahoe intersection:
* Single, left-lane closure on Arapahoe began July 19, lasting through the spring
Curtis to Champa (Block 5)
* Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=53fd561321&e=0e4069ae0b>
Champa to Stout (Block 6)
* Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=4b9584c4f3&e=0e4069ae0b>
Stout to California (Block 7)
* Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=986ac6eaa3&e=0e4069ae0b>
* South sidewalk and alleyway closure began Feb. 29, lasting through late-March. Businesses can be accessed from Stout and California streets
* Stout intersection:
* Full intersection closure began Feb. 21, lasting through late-May. See detour map here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=dc1d94f2cd&e=0e4069ae0b>
California to Welton (Block 8)
* Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=4b4b67cad8&e=0e4069ae0b>
* California intersection:
* Full intersection closure began Feb. 7, lasting through late-March. See detour map here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=a73709958d&e=0e4069ae0b>
Welton to Glenarm (Block 9)
* Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=b119c3d32c&e=0e4069ae0b>
* Welton intersection:
* Welton has been reduced to two lanes — one southbound and one northbound. This began Dec. 5 and will last through the spring
* Single northbound lane closure on Welton south of 17th Street began March 11, lasting through late-March. One southbound and one northbound lane remain open.
Glenarm to Tremont (Block 10)
* Phase 1 of improvements underway<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=995b7b6e65&e=0e4069ae0b>
* North sidewalk and alleyway closure began Feb.13, lasting through late-March. Businesses can be accessed from Glenarm and Tremont Place
* Glenarm intersection:
* Utility work is occurring on Glenarm Place and in the Glenarm intersection. This began Nov. 9, lasting through mid-April. Pedestrian and bike access is maintained
Tremont to Court (Block 11)
* Phase 1-2 Combo<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=9f8ed546b9&e=0e4069ae0b> (south side only) improvements underway
* Tremont Intersection:
* Full intersection closure began March 11, lasting through mid-April. See detour map here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=6e74bd4fb6&e=0e4069ae0b>.
* Three of the four crosswalks at each intersection will remain open. Follow signage and plastic water barriers, where present, to a safe crossing location.
Court to Cleveland (Block 12)
* Preconstruction utility work underway
* South sidewalk closure on east side of block began Jan. 10, lasting through May. Businesses can be accessed from Court and Cleveland Place
Expected Work Hours
Workdays and hours are anticipated to be Monday through Friday, 7 a.m. to 9 p.m. Weekend work will occur between 8 a.m. and 5 p.m. A noise variance was approved in January 2024 which allows work to take place throughout the night under specific circumstances<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=182f26a985&e=0e4069ae0b>. Affected parties will be notified 7 days in advance if night work will be taking place.
Heavy equipment may operate between hours of 8 a.m. to 5 p.m., any day of the week. Material deliveries and staging may occur overnight. All project activities and schedules are weather-dependent and subject to change.
Due to schedule and sequencing, not all active blocks will have activities occurring at all times. To see the latest updates on work, you can check the Current Project Activities page on the website<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=abc8fcbc9e&e=0e4069ae0b>.
RTD Free MallRide
The RTD Free MallRide continues to run during the 16th Street Mall Project, rerouted to 15th and 17th streets until the project is complete. The detour is currently from Wazee Street to Civic Center Station. For more information on RTD's Free MallRide detours, click here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=b0321d335e&e=0e4069ae0b>.
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/2faed991-00d2-0cd3-1907-9baf96946bb8.jpg]
Business Support
The City and County of Denver and the Downtown Denver Partnership have developed a Small Business Support Program<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=79126494db&e=0e4069ae0b> to assist businesses potentially impacted by 16th Street Mall construction throughout the multi-year construction period. Check if your business is now eligible on the Business Support page<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=8f78e7921e&e=0e4069ae0b> of the 16th Street Mall Project website. Questions? Email edprograms at downtowndenver.com<mailto:edprograms at downtowndenver.com>.
Connect with the Project Team
Trailer Talks are Virtual!
In an effort to increase engagement and accessibility at Trailer Talks, the project team switched to an online “office hours” format in late 2023. Each month, project team members will host a virtual office hours to provide project information and answer questions from the public. The next virtual office hours will be held on March 28, 2024 from noon – 12:30 p.m. To RSVP and receive a meeting link, click here<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=7029fd4774&e=0e4069ae0b>.<https://cig-pr.us1.list-manage.com/track/click?u=fc34ba15e6547b8d998f63f6a&id=3f3490da23&e=0e4069ae0b> If that time won’t work with your schedule, we are also happy to set up a different time to meet in-person or virtually.
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/f89662d4-68a3-0e0a-15bb-41492601f16c.png]Mobile App
Need 16th Street Mall information on the go? Download our mobile app to:
* Access the overview map of project activities
* Learn about the project and each construction phase
* Find businesses along the Mall
* Sign up for block-by-block notifications on construction impacts, phase changes and more to best plan your route
* Connect with the project team with concerns or questions from your mobile device
To download the app, go to the Apple Store or Google Play store and search “16th Street Mall Project."
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/images/454f9048-2b45-d5ef-ed24-8ccc45019d76.png]
Clean & Safe Mobile App
Directly report non-emergency public safety and maintenance concerns in Downtown Denver. The Clean & Safe Program covers the Business Improvement District for the 120 blocks of Downtown Denver, including LoDo, Upper Downtown and the Convention Center corridor.
To download the app, go to the Apple Store or Google Play store and search “Clean & Safe - Downtown Denver."
[https://mcusercontent.com/fc34ba15e6547b8d998f63f6a/_compresseds/8ddaf6a7-9081-a293-8efd-085d52a682bf.jpg]
This email was sent to garyvdrn at msn.com<mailto:garyvdrn at msn.com>
why did I get this?<https://cig-pr.us1.list-manage.com/about?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&e=0e4069ae0b&c=0062b8b12f> unsubscribe from this list<https://cig-pr.us1.list-manage.com/unsubscribe?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&t=b&e=0e4069ae0b&c=0062b8b12f> update subscription preferences<https://cig-pr.us1.list-manage.com/profile?u=fc34ba15e6547b8d998f63f6a&id=b99fd40a0e&e=0e4069ae0b&c=0062b8b12f>
CIG PR · 1660 Lincoln St Ste 1800 · Denver, CO 80264-9906 · USA
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://nfbnet.org/pipermail/colorado-talk_nfbnet.org/attachments/20240323/bd242ba0/attachment-0001.html>
More information about the Colorado-Talk
mailing list